| Work Accomplished Through April 30, 2001: |
|
Work Anticipated Through May 15, 2001: |
| 1. |
ABC Tile - Tile labor 75% |
|
1. |
ABC Tile - Tile labor 100% |
| 2. |
All tile materials received on time |
|
2. |
Chester's Trim - 100% |
| 3. |
Chester's Trim - 50% complete (doors set, Down/up base complete, crown complete up) |
|
3. |
Vintage Cabinets - 100% |
| 4. |
Metro Stairs - Stairs 100% |
|
4. |
Roman Marble - Countertops 100% |
| 5. |
Metro Sheet Metal - Gutters 100% |
|
5. |
Cabinets to be installed next week |
| 6. |
Countertops ordered & ready for install |
|
6. |
FraserCon - Flatwork complete 100% |
| 7. |
Ross Loew - Paint 15% complete (prep.,primer) |
|
7. |
All plumbing fixtures confirmed available |
| 8. |
PTI Hardwoods - 100% |
|
8. |
Scheduled Faux Finish artist for June 1. |
| 9. |
Trinity Landscape - 30% complete (sprinklers,grade) |
|
9. |
Metro Sheet Metal - Gutters 50% |
| 10. |
Hardware - Pick up |
|
10. |
Ironworks - Exterior wrought iron balcony 100% |
| 11. |
McMoran HVAC - Vents installed |
|
11. |
McMoran HVAC - Set exterior units |
| 12. |
Ari-tex Electric - Schedule for trim, alarm next 5/21 |
|
12. |
Light Fixtures confirmed available - 95% |
| 13. |
Factory Builder's Store - Schedule appliance delv (Dining room chandelier still on order ETA 5/30/01). |
|
13. |
Appliances confirmed 100% ready to ship |
| 14. |
Stone Images - Cast stone fireplace installed 100% |
|
14. |
Ferguson - Schedule plumbing fixture delivery |
|
|
|
15. |
Sound Image - Schedule low-voltage |